Been away for work all week and missed the bricks starting. I'm assuming they started on Wednesday. One full wall is done and part of the rear wall. Two courses done around the whole house and termite layer is down. Also included a photo of the view from our porch. There's a nice park across the road and the open space will never be built on.
Friday 29 April 2016
Wednesday 20 April 2016
Internal Plumbing
All the water and gas lines were run today. I got a very nasty shock to find they have put the hot water system smack bang in the middle of the wall in the backyard. Every single plan I have received shows it to be located on the side of the house on the Laundry wall. I pulled them up on it and was told that Rheem no longer make a gas boosted solar hot water system that has the gas booster piggy backed to the tank. The amount of wall space needed for the new unit is 2m and the Laundry wall was only 1910. I understand there's nothing that can be done about it but I am very unhappy about it.
Sunday 17 April 2016
Bricks Delivered
Bricks have been delivered today. They should be starting end of next week or after the long weekend if the weather holds off.
Thursday 14 April 2016
Wednesday 13 April 2016
Roof Progress
Tuesday 12 April 2016
Roof Started
Friday 8 April 2016
Gutters and Fence
Saturday 2 April 2016
Frames and Trusses
Not much has happened in the last 2 weeks from the slab being poured. External plumbing was completed before Easter but that was it. Frames were delivered on Tuesday the 29th and then nothing all week. To my surprise the full frame, trusses and windows were put up today. There's still a bit more work to do to finish off the roof but very impressed with how much they got done today. Hopefully the wood full of knots and rot will be replaced.